UNITS OF MEASUREMENT AND PAYMENT FOR VARIOUS ITEMS


UNITS OF MEASUREMENT AND PAYMENT FOR VARIOUS ITEMS

UNITS OF MEASUREMENT AND PAYMENT FOR VARIOUS ITEMS

Sl. No.
Particulars of items
Units of measurement
Unit of payment
1
Earthwork: Excavation, filling, cutting, banking
m3
100 m3
2
Surface dressing
m2
m2
3
Cutting of trees
Number
Per number
4
Stones: quarrying, blasting
m3
m3
5
Concrete : PCC, RCC, Precast
m3
m3
6
Jail works
m2
m2
7
Damp proof course
m2
m2
8
Brick work of any description
m3
m3
9
Thin partition wall
m2
m2
10
String course, drip course, water course coping etc
m
m
11
Stone work of any description
m3
m3
12
Stone work in wall facing (thickness specified)
m2
m2
13
Wood work: truss, rafter, beam etc
m3
m3
14
Door, window shutters
m2
m2
15
Door, window fittings
Number
Per number
16
Timbering, boarding, sawing of timber, timbering of trenches, partition, etc
m2
m2
17
Steel work
Quintal
Per quintal
18
Expanded metal, fabric reinforcement, cutting angles, plates, tees
cm2
cm2
19
Threading; welding; solder of sheets
cm
Per cm
20
Iron gate, grill collapsible gate, rolling shutter
m2
m2
21
Iron railing
m
m
22
Roofing: tiled, corrugated iron, caves board (thickness specified)
m2
m2
23
Centering, shuttering
m2
m2
24
Ridges; valleys; gutters (girth given)
m
m
25
Expansion and contraction joints
m
m
26
Ceiling timber, A.C. sheet, board, etc
m2
m2
27
Plastering; pointing; white washing; distempering; painting; varnishing; polishing; coal tarring; removing of paints
m2
m2
28
Flooring of any kind
m2
m2
29
Pipes, laying of pipes
m
m
30
Dismantling of brick masonry
m3
m3
31
Grouting
m2
m2
32
Grouting of cracks, joints
m
m
33
Supply of sand; brick ballast; aggregates; timber
m3
m3
34
Supply of cement
Bag
Per bag
35
Supply of steel, G.I. sheet, bare electric line
Quintal
Per quintal
36
Supply of GI sheet
m2
m2
37
Supply of sanitary items
Number
Per number
38
Supply of paint, varnishes
Litre
Per litre
39
Supply of explosives, stiff paint
Kg
Per kg